How to Estimate a Tile Shower (Waterproofing, Shower Base, Labour)
By Fabio Freire, Founder & General Contractor at EZ-Estimates. Published 2026-11-08.
A tile shower looks like a simple box. It is not. It is a waterproof system with a sloped floor, a curb, a niche, three walls of cuts, and a 24 hour wait in the middle where nobody can touch it.
That is why tile showers eat margin. Contractors price the tile and forget the system. Then the job runs two days long and the profit is gone.
Here is how to estimate a tile shower line by line, with a worked example you can copy.
Why Tile Showers Get Underpriced
Most bad shower bids miss the same four things:
- Waterproofing is priced as a material, not a phase. It takes time to install, time to cure and a day to flood test.
- The shower base is a guess. Mortar bed, foam pan or linear drain kit all price very differently.
- Wall tile is priced per square foot like a floor. Walls have more cuts, more trim and slower setting.
- Small items are left off. Niche returns, curb pieces, edge trim, corner sealant, grout sealer.
For reference, This Old House puts a midrange tiled walk-in shower at $8,000 to $13,000, and high-end custom showers at $14,000 to $20,000 and up. If your bid lands far below that for a full tear-out and rebuild, check what you missed.
Step 1: Measure Every Surface
Measure the floor, each wall and the curb separately. Do not use one "shower size" number.
- Floor: length x width of the shower base.
- Walls: width x tile height for each wall. Most showers tile to 84 to 96 inches, or to the ceiling.
- Niche: back panel plus the four returns (top, bottom, two sides).
- Curb: top plus both faces, times the curb length.
- Openings: subtract windows. Do not subtract valve or shower head holes.
Write down the tile size for each surface. A 2x2 mosaic floor and 12x24 walls are two different estimates.
Step 2: Count Tile, Then Boxes
Square feet is not what you buy. You buy boxes and sheets.
- Add waste to each surface. Straight lay is usually around 10%. Herringbone, diagonals and large format with lots of cuts run 15% or more. Our waste factor guide has the numbers by trade.
- Divide by the square feet per box (or pieces per box) from the supplier.
- Round up to full boxes. Then add one box from the same lot for repairs if the client wants spares.
Quick sanity check: the free tile calculator with waste gives you a fast count for a single surface.
Step 3: Price the Waterproofing System
This is where showers fail and where callbacks come from. Price it as its own section.
What goes in it:
- Backer board or foam board on the walls
- Waterproofing membrane on walls, floor, curb and niche (sheet membrane like Schluter KERDI, or a liquid membrane)
- Seam band, inside and outside corners, pipe and valve seals
- Membrane-compatible drain
- Thinset or adhesive for the membrane
- Flood test
Cost benchmarks: Inch Calculator puts waterproofing at about $1 to $2 per square foot for materials and installed backer board at $5 to $6 per square foot. This Old House lists a backer board and waterproofing system at $800 to $1,500 for a typical shower.
The flood test is a schedule item. Plug the drain, fill the pan with about 2 inches of water and leave it. Many inspectors and manufacturers want 24 hours. LATICRETE, for example, says to wait at least 24 hours after installing its HYDRO BAN shower pan before flood testing. That is a lost day on site. Put it in your schedule and your labour plan, not just your materials.
Step 4: Choose and Price the Shower Base
The base drives price, labour and risk more than any other item.
| Shower base |
What it is |
Typical cost (This Old House) |
| Prefabricated pan |
Acrylic or fibreglass base, no floor tile |
$800 to $1,500 |
| Custom tile pan |
Sloped mortar bed or foam tray, then tile |
$1,200 to $3,000 |
For a tiled base, the floor must slope to the drain. A minimum of 1/4 inch per foot is the common rule. The City of Sammamish shower subpan guide, for example, requires at least 1/4 inch per foot at the subpan level.
Mortar bed (traditional): cheapest material, most labour. Pre-slope, liner, then a mortar bed. Plan most of a day before any tile.
Foam tray with bonded membrane: costs more in materials, saves hours. Good for crews doing many showers.
Linear drain or curbless: the most labour and the most planning. The floor may need to be recessed into the joists. Price this as a custom item, never as a standard pan.
Liner height above the curb and test rules vary by code and city. Check your local plumbing code and inspector before you bid.
Step 5: Estimate Labour by Phase
Price labour by phase, not by one square foot number. Tile showers have too many steps for a flat rate.
| Phase |
Typical crew time (alcove shower) |
| Demo and haul away |
0.5 to 1 day |
| Framing fixes, blocking, niche framing |
0.5 day |
| Backer board and shower base |
0.5 to 1 day |
| Waterproofing |
0.5 day |
| Flood test (waiting) |
1 day |
| Wall tile |
1.5 to 2.5 days |
| Floor tile, curb, niche, trim |
0.5 to 1 day |
| Grout, caulk, seal, clean |
0.5 day |
That is roughly 5 to 8 days on site for a standard alcove shower, before glass. Your own crew speed is the real number. If you are not sure how to turn days into a rate, see how to calculate construction labor costs.
Step 6: Add the Small Items Everyone Forgets
- Edge trim or bullnose for outside corners and the tile edge
- Curb cap tile or a solid surface curb
- Niche shelf or a matching tile shelf
- Thinset, grout and grout sealer (large format needs more thinset per square foot)
- 100% silicone for change of plane joints
- Tile leveling clips for large format walls
- Protection for the tub, floor and vanity area
- Disposal fees
Worked Example: 3 x 5 ft Alcove Shower
Here is the takeoff for a 36 x 60 inch alcove shower tiled to 7 ft, with a 2x2 mosaic floor and 12x24 porcelain walls.
Surfaces:
- Floor: 3 x 5 = 15 sq ft
- Back wall: 5 x 7 = 35 sq ft
- Side walls: 3 x 7 x 2 = 42 sq ft
- Niche (12 x 24 with 4 inch returns): about 4 sq ft
- Curb (5 ft long, top plus two faces): about 6 sq ft
Tile count:
- Walls and niche: 81 sq ft + 10% waste = 89 sq ft. At 16 sq ft per box, that is 6 boxes.
- Floor and curb: 21 sq ft + 15% waste for mosaic cuts = 24.2 sq ft. At 1 sq ft per sheet, that is 25 sheets.
Waterproofing: about 105 sq ft of membrane to cover walls, floor, curb and niche with overlaps.
Labour: about 6 days, including the flood test day.
Now plug in your own supplier prices and your day rate. Add markup on materials and your overhead. If you need help setting that number, read what markup a contractor should charge.
Common Tile Shower Estimating Mistakes
- Forgetting the flood test day
- Leaving the niche and curb out of the tile count
- No allowance for rotten subfloor or framing behind the old tub
- Letting the client pick tile after the bid, with no allowance written in
Write a tile allowance into the estimate (for example, "tile allowance $6 per sq ft") so a $25 per sq ft marble pick becomes a change order, not your loss.
How EZ Tile Speeds This Up
All of the steps above are measuring, counting and rounding. That is what EZ Tile, the tile layout tool inside EZ-Estimates (now in early access), is built for.
- Get the room in. Scan it with an iPhone using LiDAR, or pull it from EZ Floor Plan, with doors, windows, tub and vanity.
- Say the layout. Type or talk: "2x2 on the floor, 12x24 on the walls."
- Pick the best layout. EZ Tile compares layouts for the best look, the least waste and the fewest cuts.
- Get the order list. It counts tiles and boxes from your pieces per box, plus thinset and grout, and handles niches with returns and edge trim.
- Show the client. See the layout on 3D walls, then send a clean tile quote PDF.
The numbers flow into your EZ-Estimates estimate, where you add waterproofing, base and labour lines and send it the same day. Try it free and price your next shower before you leave the driveway.
FAQ
How much does it cost to tile a shower?
This Old House puts a midrange tiled walk-in shower at $8,000 to $13,000. Inch Calculator estimates $20 to $30 per sq ft for tile installed on shower walls, before the base, plumbing and glass.
How much waste should I add for shower tile?
Around 10% for straight lay on walls. Plan 15% or more for mosaics, herringbone, diagonal layouts or large format tile with many cuts.
What slope does a shower floor need?
At least 1/4 inch per foot toward the drain is the common requirement. Confirm with your local code.
How long is a shower flood test?
Many inspectors and membrane makers want about 2 inches of water held for 24 hours. Check your inspector and the membrane maker's instructions.